Friday, April 25, 2008

Mandating Velocity

Assume you are in the middle of preparing your release plan. The team - product managers, developers, performance engineers, user interface experts, and other - has come back with a plan that is based on a velocity of let's say 3.56 per week.

You are certainly interested in any improvement of speed. So you are considering to say: What if you would plan for 4 per week? Or maybe you are even considering to mandate a velocity of 4. Would that be a smart idea?

Let's have a look back to the "good old days". A manager describes a piece of work to one of his engineers and asks for the estimated effort required to do the job. The engineer comes back and says that he can build it in 28 days. The manager thinks about it and then says: I think you can build it in 25 days. You will get 25 days to build it. I expect it by ... (fill in a date).

What's wrong with this? For one, if the engineer is not stupid next time he will add what he thinks will removed from his estimate (3 days) plus some (maybe 2 days) in case the cuts are higher next time. So the initial estimate might be 32 days. The manager is not stupid either. Next time he might think that the estimates are "inflated" anyways and that "sand bagging" happens anyways and sure people are playing ping-pong or darts anyways. So it's safe to reduce the estimates by 10% or even more. Just to get to the "real" numbers.

All of this leads to a situation where nobody works with the real numbers anymore. Every single estimate becomes unreliable and as a consequence every project plan built on them is flacky and unreliable on the outset. The engineer and - using the approach on a large scale - the entire team is set up for failure. (Unless you don't have a problem with "whipping" them a little harder and expect them to work crazy hours, which may not be a problem for as maybe you don't have family and don't know how it feels when you miss important events in the lives of your kids.)

There are certainly chances that the engineer may finish the work in 25 instead of 28 days. But at what price? If it really takes that long to do the job properly and if the engineer is really working at the maximum sustainable pace then what is left? Quality. The only choice the engineer is left with is degrading quality. This could mean that code is no longer reviewed. It could mean that design is no longer reviewed. It could man that some error handling code is left out (good chances it won't get caught in system testing). It could mean that fewer tests are written or no tests at all.

How is this related to the initial story around a velocity of 3.56 versus 4? Well even if you don't challenge the estimates, mandating an increased velocity is in essence the same thing. You are saying that people are not working hard enough, are in cruise-mode, etc.

Eventually the velocity will increase. The numbers will go up, they will even achieve 5, 6, or any number that you choose. Just by osmosis the team will learn about your "technique" and it will adapt. The estimates for every single item will go up. If an item was estimated to be 2 it will then be 3 (or even 20!). Then the velocity will increase not only to 4 but they will achieve a breath taking 35! Just imagine!

But seriously. If you are interested in working with the true numbers so that you have realistic and reliable plans that you can base important decisions on then you shouldn't mandate velocity.

A different question is certainly when there is a project that is very critical to the company. If you have treated your people with openness, honesty, and fairness, I'm sure they will understand if as an exception extraordinary measures needs to be taken. However, if those are used in every other release cycle, it becomes normal mode of operation and hence unsustainable.

It all boils down to how you select your "supplier". Are you interested in getting only the cheapest one, no matter what? Or are you interested in a reliabel supplier that continuously reduces the cost / increases the output / improves the quality? -As a customer as well as a manager this is your choice. (My take on this: Sacrificing quality has never ever paid off.)

Wednesday, February 06, 2008

Monitoring and Tracking Projects

Need a template for monitoring and tracking your project? Here you go. We have created a simplified version of the tool we are using in our projects, too. The spreadsheet is prefilled with a sample backlog for a hypothetical project. It assumes sprints of 1 week and a release cycle with 12 sprints.

The template includes graphs for the actual velocity and a burn down graph. If you have questions and/or suggestions for improving the template please use the contact details at the Agile Utilities web site.

Oh, and here is the most important link, the link to Agile Tracker. And of course this template is free.

Wednesday, January 23, 2008

A Nice Story On Estimates

The stereotypical conversation between a manager and a software engineer in a more traditional company goes as follows:

Manager: "I have this piece of work. How long does it take you to complete this?"

Engineer: "It'll take me about 2 months."

Manager: "That's great but let's push the envelope. I think you can do it in 1.5 months."

This is overruling the estimates, and in my experience a big no-no. It is ok and depending on circumstances even helpful to ask guiding questions. E.g. you might want to ask: "What if we implemented this using [xyz] ?" or "Did you consider [abc]?"

Guiding questions help avoiding over-engineering or misunderstandings in the first place.

Today I experienced a different dialog. The manager in the following scene was me:

Manager: "I have this piece of work. How long do you think will it take to complete this?"

Engineer: "It will take about 2 months."

Manager: "Ok, so to be on the safe side, should we say it takes 3 months?"

Engineer: "It will take about 2 months."

And then he went deep into the details to explain to me what tasks would be required for the job.

Bottom line: I observed something extremely positive here. The engineer insisted on his estimate, and I think he was right. He was the person closest to the problem and with the best expertise to make the call. How could I dare to question this if I didn't have better arguments?

Ben, who was the engineer in this particular case, showed me that the above rule also works the other way round. Don't just change the estimates if your best engineers give you an estimate. And this applies for both, decreasing and increasing the estimates. Thank you, Ben! I shouldn't have questioned your judgement in the first place.

Thursday, January 17, 2008

Impact and Mitigation of Staff Turnover

In my last post I explored the reasons for staff turnover. Reasons can be monetary (e.g. salary) and non-monetary. In all cases the departure of a team member has consequences, some of which may become visible months later.

Example. For one release cycle a project team signed up for a backlog of 70 stories. Two weeks into the release cycle (12 weeks in total) the team got together and identified a few stories that were too large to fit into one iteration (1 week). As a consequence the backlog grew to 80 stories. The team asked the customer to re-prioritize the stories to identify the low priority stories that would have to be moved to a future release. Not surprisingly, the customer wasn't happy about this as it was perceived as "falling behind schedule". On closer investigation it turned out that the initial backlog contained stories that were too big for acceptance. These stories should have been split or re-scoped before the release cycle started. The person who would have spotted this had left the company just a few months ago. Other team members weren't sufficiently aware of the impact large stories could have. The team learned their lesson and it is unlikely that the same mistake will be repeated.
The important lesson to be learned is: The consequences of the departure of a staff member become apparent only as time passes, and sometimes this can be much, much later.

How could the mistake from the example be avoided? I think that it is important to re-emphasize the rules of the game as often as possible. You might sound like a "broken record". But consider the consequences if you don't repeat "the tune"...

The example also demonstrates that when a team member leaves, some knowledge and skills disappear as well. What are the options to mitigate the impact?

Agile methodologies provide quite a few techniques and tools that you can use. In particular all techniques and tools that foster communication, collaborations, and learning are suited to reduce or mitigate the impact to a large degree.

Release planning involving a good cross cut of different roles - developers, testers, customers, performance experts, technical writers, etc. - ensures that all relevant aspects are considered. Techniques like Agile Auction (aka Planning Poker (TM)) help to detect uncertainties or the need for further discussions.

Frequent reviews help to identify over- or under-engineering. Do you really need all these bells and whistles? Are the features implemented in a really compelling way?

Techniques and tools like Pair Programming, wikis and Show-and-Tells help fostering knowledge transfer and the acquisition of skills.

Keep it simple and try tons of different tools and techniques. Don't give up just because one tool or technique didn't work. If it didn't work, try something else. Learn from your observations. And always challenge your team for instance by asking questions like:
  • Given this unsatisfying result can you think of a way how we can prevent a similar situation in the future?
  • Given the suggested approach, can we think of an even better way of doing this?
Experiment and try new approaches. Doing that you'll have mitigate a large proportion of the possible impact of turnover.

Saturday, August 19, 2006

Dealing With Uncertainty in Stories

Extreme Programming uses stories to define the scope of a system. Sometimes teams have difficulties to estimate the size of stories with a satisfying accuracy. Different approaches to address this issue are possible, e.g. making stories even smaller.

Another approach is to look for the elements in a story that represent the risk. Then these elements can be addressed in a time-boxed spike (or experiment). The remainder stays thus becomes a low risk story.

Risky elements may be new technologies that need to be tried first, or a cool new user interface widget. An example of the later could mean that you might want to implement a simple (maybe even un-cool) version of the interface first. And separately you play the story with the spike for the cool widget. That way you deliver value while at the same time pushing the envelope in a time-boxed fashion. If the outcome of the spike is good then you can play a third story to improve the user interface.

With this approach I have seen different teams addressing risk, and at the same time improve their estimation skills. There are certainly more techniques. If you know of another simple way to deal with this I would be interested to hear from you.