Friday, April 25, 2008

Mandating Velocity

Assume you are in the middle of preparing your release plan. The team - product managers, developers, performance engineers, user interface experts, and other - has come back with a plan that is based on a velocity of let's say 3.56 per week.

You are certainly interested in any improvement of speed. So you are considering to say: What if you would plan for 4 per week? Or maybe you are even considering to mandate a velocity of 4. Would that be a smart idea?

Let's have a look back to the "good old days". A manager describes a piece of work to one of his engineers and asks for the estimated effort required to do the job. The engineer comes back and says that he can build it in 28 days. The manager thinks about it and then says: I think you can build it in 25 days. You will get 25 days to build it. I expect it by ... (fill in a date).

What's wrong with this? For one, if the engineer is not stupid next time he will add what he thinks will removed from his estimate (3 days) plus some (maybe 2 days) in case the cuts are higher next time. So the initial estimate might be 32 days. The manager is not stupid either. Next time he might think that the estimates are "inflated" anyways and that "sand bagging" happens anyways and sure people are playing ping-pong or darts anyways. So it's safe to reduce the estimates by 10% or even more. Just to get to the "real" numbers.

All of this leads to a situation where nobody works with the real numbers anymore. Every single estimate becomes unreliable and as a consequence every project plan built on them is flacky and unreliable on the outset. The engineer and - using the approach on a large scale - the entire team is set up for failure. (Unless you don't have a problem with "whipping" them a little harder and expect them to work crazy hours, which may not be a problem for as maybe you don't have family and don't know how it feels when you miss important events in the lives of your kids.)

There are certainly chances that the engineer may finish the work in 25 instead of 28 days. But at what price? If it really takes that long to do the job properly and if the engineer is really working at the maximum sustainable pace then what is left? Quality. The only choice the engineer is left with is degrading quality. This could mean that code is no longer reviewed. It could mean that design is no longer reviewed. It could man that some error handling code is left out (good chances it won't get caught in system testing). It could mean that fewer tests are written or no tests at all.

How is this related to the initial story around a velocity of 3.56 versus 4? Well even if you don't challenge the estimates, mandating an increased velocity is in essence the same thing. You are saying that people are not working hard enough, are in cruise-mode, etc.

Eventually the velocity will increase. The numbers will go up, they will even achieve 5, 6, or any number that you choose. Just by osmosis the team will learn about your "technique" and it will adapt. The estimates for every single item will go up. If an item was estimated to be 2 it will then be 3 (or even 20!). Then the velocity will increase not only to 4 but they will achieve a breath taking 35! Just imagine!

But seriously. If you are interested in working with the true numbers so that you have realistic and reliable plans that you can base important decisions on then you shouldn't mandate velocity.

A different question is certainly when there is a project that is very critical to the company. If you have treated your people with openness, honesty, and fairness, I'm sure they will understand if as an exception extraordinary measures needs to be taken. However, if those are used in every other release cycle, it becomes normal mode of operation and hence unsustainable.

It all boils down to how you select your "supplier". Are you interested in getting only the cheapest one, no matter what? Or are you interested in a reliabel supplier that continuously reduces the cost / increases the output / improves the quality? -As a customer as well as a manager this is your choice. (My take on this: Sacrificing quality has never ever paid off.)

Saturday, February 09, 2008

Agile and Free Flow of Information

In his February 07 blog post ManagePro's CEO Rodney Brim discusses the relationship between being fast and managing information.

I like his post very much. However, ... in my post I'd like to discuss one particular aspect that I think needs some further discussion.

Rodney writes: "...the relationship between being fast or Agile and how..." - I think that being fast is not the same as being agile. I think that agile is about adaptability while being fast is about efficiency. Agile is about the ability to adapt for keeping the business fit in an fast-changing environment. Learning about changing environments and learning from past experiences requires the storage, retrieval, and distribution of information.

A lot of companies use paper or it's electronic equivalent for storing and transmitting information. While this has it's benefits for long-term storage - with proper backups it lasts forever - it has also it's drawbacks.

For instance, if I need a piece of information and I can easily recall it from my memory then this is the fastest to obtain it. If I have a colleague sitting next to me who I can ask and he has the information available then that's probably the next best solution. If I have to sit in front of a computer and enter a query I might get pages and pages of search results, even if I am fortunate enough to have a specialized search engine or even if the body of knowledge is stored in a good intra-corporate wiki. So this type of search tends to be very slow.

So depending where information is stored and what kind of access path I have, information is easy or harder to obtain.

But there is at least one more aspect. When two or more people communicate they again can choose different media to exchange information. After all, whatever one person is saying to a different person is nothing more than sending a small piece of information even if the content might be very simplistic. "How are you?" might carry the information about me caring about the other person. Saying "How are you?" in a face-to-face situation has a different effect than saying the same words on the phone, writing the same sentence in a hand written letter, or writing them in an email.

When I work with my people from my team or people from other teams, e.g. stakeholders, suppliers, customers, I am always on the lookout for difference in understanding of different people. When I spot such a difference I try to organize a face-to-face meeting of those people. I try to get them into one room and make them talk to each other.

I also share with my team as much information as I can. Although this certainly has it's limitations where privacy reasons of individuals or confidentiality of company information gets into the game, but it is an important factor for establishing trust.

Here is another way to describe my approach: In order to make my team more agile I try to "grease" the free flow of information. Only if the important information gets to every team member as quickly as possible the team can react in a timely fashion.

The same applies to reporting. I create reports on a weekly basis for the projects I'm responsible for. The stakeholders are informed at the earliest possible time of opportunities and challenges. Giving enough heads-up time with accurate information is probably one of the best things you can do to support your manager and other stakeholders.

So in that sense a lot of the information we circulate in my teams becomes tacit knowledge in the brains of the people.

As that is not always the best way to store information we also employ a wiki for information that we believe is valuable for long-term storage. And there are other media that we use as well such as spreadsheets, pion-boards, white-boards, etc.

So to become an agile organization it is important to use the most appropriate medium and channel for distributing and sharing information. As a collateral it is interesting to see that an organization that is very adaptible - that is agile - is at the same time also very lean and as a consequence very efficient and fast. In contrast a fast organization might be highly efficient and might be able to process service requests, product manufacturing, or software development tasks extremely fast. But if the environment changes that very same organization might have tremendous difficulties to adapt to the new conditions.

There is (at least) one more way of looking at this: Being fast is about optimizing towards efficiency while being agile is about optimizing towards adaptability. Both can be competing objectives at times.

In summary: I believe that an agile organization is very likely to be fast. But a fast organization is not necessarily agile. The other item I learned from practice: Free Flow of Information improves an organizations adaptability.

Wednesday, January 23, 2008

A Nice Story On Estimates

The stereotypical conversation between a manager and a software engineer in a more traditional company goes as follows:

Manager: "I have this piece of work. How long does it take you to complete this?"

Engineer: "It'll take me about 2 months."

Manager: "That's great but let's push the envelope. I think you can do it in 1.5 months."

This is overruling the estimates, and in my experience a big no-no. It is ok and depending on circumstances even helpful to ask guiding questions. E.g. you might want to ask: "What if we implemented this using [xyz] ?" or "Did you consider [abc]?"

Guiding questions help avoiding over-engineering or misunderstandings in the first place.

Today I experienced a different dialog. The manager in the following scene was me:

Manager: "I have this piece of work. How long do you think will it take to complete this?"

Engineer: "It will take about 2 months."

Manager: "Ok, so to be on the safe side, should we say it takes 3 months?"

Engineer: "It will take about 2 months."

And then he went deep into the details to explain to me what tasks would be required for the job.

Bottom line: I observed something extremely positive here. The engineer insisted on his estimate, and I think he was right. He was the person closest to the problem and with the best expertise to make the call. How could I dare to question this if I didn't have better arguments?

Ben, who was the engineer in this particular case, showed me that the above rule also works the other way round. Don't just change the estimates if your best engineers give you an estimate. And this applies for both, decreasing and increasing the estimates. Thank you, Ben! I shouldn't have questioned your judgement in the first place.